Academic & Residential Complex
Opening Fall 2019





















About The Academic & Residential Complex

This new integrated living-learning community located near Harrison and Morgan Streets is more than 151,000 square feet. The 10-story building will provide residential accommodations for approximately 550 students in a traditional and semi-suite style environment. Within the residential footprint, approximately 16,000 square feet will feature a fitness center, a large academic lounge, laundry facilities, social & study lounges on each floor and a tenth-floor sky lounge.

Attached to the residential building is the classroom building with over 50,000 square feet of academic space. This area includes three large lecture halls, four classrooms, multiple small group study rooms, a tutoring center, computer stations and several collaboration spaces. Among the classrooms, the largest 258-seat classroom can also be transformed into a flexible event and performance space. This space will also include instructional spaces with “turn to team” design elements, a learning oasis, and a C-Stop. The retail space, anticipated to be used as a cafe, will be approximately 1,600 square feet of the project.

Construction Schedule

June 2018
  • Exterior Work - Steel & Concrete Work

    Complete structural steel and concrete work on the Academic Building. Precast panel installation on the Residence Tower. Window installation on the Residence Tower. Start of Roofing work. Continue Build out of the interior spaces on the Residence Tower

July 2018
  • Interior Construction - Residence Tower Interior Work

    Start interior mechanical work on Academic Building. Start Grand Staircase work in Academic Building. Start Low Voltage Work. Permanent Power to the building to be completed.

August 2018
  • Interior Construction - Academic & Residence

    Start Academic Building Build Out. Residence Tower Elevator Work to start

September 2018
  • Exterior - Paving

    Site sidewalks and paving work to begin

April 2019
  • Exterior - Paving

    Landscaping Work to begin

May 2019
  • Exterior - Finishing

    Final Finishes Installed. Building Commissioning

July 2019
  • Interior - Finishing

    Furniture, Fixtures and Equipment installed.